Demolition Environmental Enabling Civil Engineering Plant Hire

West Ham Boleyn Stadium

- 05/11/20

Overview

Client: Barratt East London

Value: £2,800,000

Programme: 10 months

Overall Recycle percentage: 98%

Description

This project required the dismantling and demolition of the iconic 35,000-seater Premier League football stadium, including the removal of asbestos and all foundations and obstructions.

The complex contract programme of work comprised dismantling of the cantilevered football stands and the removal of massive steel sections in a controlled environment, as well as the demolition of stand structures and the removal of extensive foundations. The site was within a residential area and directly adjacent and overhanging the local church, which required detailed planning and execution of the demolition operations.

The demolished brick and concrete was recycled and re-used in the new development and the contract was completed on time and within the original budget.

Memberships And Accreditation Partners

BSC Logo
ISO 14001
ISO 45001
ISO 9001
NFDC
NDTG
SMAS
Build UK
FORS Silver
Construction Line Gold
Acclaim
CHAS Premium Plus
Considerate Contractors
CQMS